PMI Project Management Professional (PMP) practice questions

10 questions from the bank behind this course's timed mock. Free to read and to answer, no account needed, and each has its answer and an explanation. They belong to PMI Project Management Professional (PMP) Exam Prep.

Answer them one at a time →Read lesson 1 free

  1. Question 1

    Tomás has an associate's degree and an active CAPM certification. He has led projects for 48 months. He wants to apply for the PMP this month. Based on the eligibility routes described in the lesson, what is the best assessment of his position?

    1. He does not yet qualify. His route needs 60 months of experience leading projects, so he is 12 months short.
    2. He qualifies now. His active CAPM replaces the extra experience, so 36 months of leading projects is enough.
    3. He qualifies now, but he must also complete 35 hours of project management training in addition to his CAPM.
    4. He does not yet qualify. He must first earn a four-year degree, because the PMP needs one.
    Show the answer

    Answer: A. He does not yet qualify. His route needs 60 months of experience leading projects, so he is 12 months short.

    The secondary diploma or associate's degree route needs 60 months of experience leading projects, and the CAPM meets only the education part. The 36-month figure belongs to the four-year degree route, and a CAPM does not shorten the experience requirement.

  2. Question 2

    You are the team facilitator on an agile team. Halfway through an iteration, the burndown chart shows the team is well behind the pace needed to meet the iteration goal. Your goal is to support delivery while respecting the team's authority over how the work is done. What should you do?

    1. Submit a change request to extend the iteration by one week
    2. Keep the burndown chart visible and encourage the team to raise the problem at the daily stand-up so they can adapt their own plan
    3. Reassign the remaining tasks among the developers so the work is spread more evenly
    4. Analyse the schedule variance against the baseline and present a corrective action plan to the team
    Show the answer

    Answer: B. Keep the burndown chart visible and encourage the team to raise the problem at the daily stand-up so they can adapt their own plan

    In agile, slipping progress is made visible and the self-organising team adapts its own plan, with the facilitator acting as a servant leader. Analysing variance against a baseline and planning corrective action is a correct predictive response, but here it takes a decision away from the team that owns how the work is done.

  3. Question 3

    You are the project manager on a predictive office-relocation project. Your assessment matrix shows three gaps: the sponsor (high influence, high impact) is at C = Supportive, D = Leading; a facilities clerk (low influence, low impact) is at C = Unaware, D = Neutral; the HR director (high influence, high impact) is at C = Resistant, D = Supportive. You have limited time this week. Which gap should you work on first?

    1. The sponsor, because the sponsor must always be engaged before anyone else
    2. The HR director, because they have high influence and impact and are resisting the change
    3. The facilities clerk, because Unaware is the largest gap from the desired level
    4. All three at once, by sending a single project update email to every stakeholder
    Show the answer

    Answer: B. The HR director, because they have high influence and impact and are resisting the change

    You rank gaps by the stakeholder's influence and impact. A high-influence stakeholder who is resisting is the biggest threat to the objectives, so you deal with that gap first. The clerk's gap looks large on the matrix, but the clerk has little influence or impact, so that gap comes lower on the list.

  4. Question 4

    Halfway through a predictive project, the monthly risk summary for the steering committee stops arriving. The project manager finds that the communications plan lists the audience, content, method (email) and frequency for this report, but each team lead assumed someone else was sending it. What should the project manager do to prevent this from happening again?

    1. Increase the report frequency from monthly to weekly so a missed report is noticed sooner
    2. Update the communications plan to name one person responsible for sending the risk summary
    3. Add an escalation path to the plan so the steering committee can complain when a report is late
    4. Move the risk summary to the project wiki so the steering committee can pull it whenever they need it
    Show the answer

    Answer: B. Update the communications plan to name one person responsible for sending the risk summary

    The plan item had no owner, which is one of the five core elements, so nobody took responsibility for sending the report. An escalation path is a useful extra, but it only reacts after a report is missed and does not fix the missing owner.

  5. Question 5

    During refinement, a product owner presents this story: "As a dispatcher, I want the route planner to be fast and user-friendly, so that I can plan deliveries efficiently." Developers say they cannot tell when the story would be finished. Which INVEST criterion is the story weakest on, and what is the best fix?

    1. Negotiable; turn the story into a fixed specification so the details cannot change
    2. Testable; agree specific, observable acceptance criteria with the product owner before the work starts
    3. Small; split the story into thin end-to-end slices by workflow step
    4. Independent; combine the story with the stories it depends on
    Show the answer

    Answer: B. Testable; agree specific, observable acceptance criteria with the product owner before the work starts

    "Fast and user-friendly" gives no clear criteria to show whether the story works, so it fails Testable, and the fix for a vague story is to add acceptance criteria. Splitting deals with stories that are too big, but nothing here suggests the story will not fit inside one iteration.

  6. Question 6

    A project manager is estimating a flooring installation for a new office. The organisation has reliable data from several past projects showing that a crew lays 25 m² per day, and the effort grows in a straight line with floor area. The new site needs 1,500 m². The sponsor wants an estimate that is more accurate than a rough comparison, but the detailed work packages have not been defined yet. What should the project manager do?

    1. Use bottom-up estimating by adding up estimates for each work package
    2. Use parametric estimating, which gives about 60 days
    3. Use a triangular three-point estimate from the crew's optimistic, most likely and pessimistic values
    4. Use analogous estimating based on the total duration of last year's office fit-out
    Show the answer

    Answer: B. Use parametric estimating, which gives about 60 days

    The historical unit rate is reliable and the work scales in a straight line, so parametric estimating (1,500 ÷ 25 = 60 days) fits best. Bottom-up would be more accurate, but it needs the detailed work packages that do not exist yet.

  7. Question 7

    You are the project manager on a predictive project with an outsourced software seller. During a site visit, your lead engineer tells the seller's on-site team to add three reporting dashboards that are not in the statement of work. He says it will save time later. The seller builds the dashboards and sends an invoice for the extra work. Only the procurement administrator has contracting authority. What should you do?

    1. Refuse the invoice outright, because the extra work was never added to the contract
    2. Escalate the invoice to the project sponsor and ask the sponsor to decide whether to pay
    3. Pay the invoice right away, because the work is done and the buyer's team asked for it
    4. Record the facts of the verbal instruction and send the matter through contract change control with the procurement administrator
    Show the answer

    Answer: D. Record the facts of the verbal instruction and send the matter through contract change control with the procurement administrator

    The engineer's verbal direction may have created an unauthorised constructive change, and only the person with contracting authority can change the contract, so the matter goes to contract change control with the facts on record. An outright refusal ignores that the buyer's own representative directed the work, and it invites a claim instead of settling the matter at the lowest level.

  8. Question 8

    You are the project manager for an agile team. For the last two sprints the sprint burndown chart has been almost flat. The product owner wants to replace two developers because 'nothing is getting done.' The team says it finished several stories in each sprint. Before anyone acts, you want to know what is really happening. What should you do?

    1. Accept the burndown as proof of a stall and agree to replace the developers
    2. Redraw the ideal line on the burndown so that it matches the team's actual progress
    3. Ask for a burnup chart that plots total scope and completed work as separate lines
    4. Compare this team's velocity with the other teams' velocity to see whether it is underperforming
    Show the answer

    Answer: C. Ask for a burnup chart that plots total scope and completed work as separate lines

    A flat burndown can mean the team stalled, or it can mean finished work was cancelled out by work that was added or re-estimated. A burnup separates scope change from team performance. Comparing velocity across teams is invalid because story points are relative to each team, and the comparison encourages point inflation.

  9. Question 9

    You lead a hybrid team that uses an impediment board with columns Raised → Working → Escalated → Removed. At the start of the sprint, a card saying "Vendor sandbox credentials not issued" was raised. Today, six days later, it is still in Working. The team has worked around it where it could, and you have emailed the vendor contact twice with no reply. Two backlog items tied to the sprint goal now depend on the sandbox. What is the BEST next step?

    1. Treat the card's age as a signal that your current actions are not working. Confirm the impact on the sprint goal, then escalate through the governance path with options and a recommendation, and move the card to Escalated.
    2. Add a new entry to the risk register saying the vendor may not issue credentials, and assess its probability and impact.
    3. Leave the card in Working and add the item to the retrospective agenda so the team can discuss vendor responsiveness at the end of the sprint.
    4. Ask the two developers to build their own mock sandbox so they can continue, and close the card as Removed.
    Show the answer

    Answer: A. Treat the card's age as a signal that your current actions are not working. Confirm the impact on the sprint goal, then escalate through the governance path with options and a recommendation, and move the card to Escalated.

    A card that sits for days shows the impediment needs more help. Your own actions have failed and the sprint goal is now at risk, so escalating with options is right. The workaround option is wrong because it leaves the cause in place and closes a blocker that has not actually been removed.

  10. Question 10

    A project manager is leading a hybrid project that replaces a manual stock-tracking process. Senior storeroom clerks keep finding reasons to delay the pilot. In private conversations, the project manager learns that the clerks built the current process and fear they will lose their standing as the go-to experts. The project manager wants to turn this group into supporters before the next release. What should the project manager do?

    1. Schedule extra feature-by-feature training for the clerks so they are confident with the new tool
    2. Invite the senior clerks to act as change champions who test early increments and coach their colleagues
    3. Ask the sponsor to send a message that stresses the pilot dates are mandatory
    4. Raise a change request to keep the old process running alongside the new one
    Show the answer

    Answer: B. Invite the senior clerks to act as change champions who test early increments and coach their colleagues

    The cause is fear of losing status, so the right response is involvement and a champion role, which keeps the clerks' expertise visible. More training addresses a lack of ability, which is not the cause found here.

The full timed mock

60 questions in 77 minutes, with a pass mark of 70%. Each paper is drawn from a bank of questions written for the mock alone, and these 10 are left out of it. Full access opens it, with every level of the course.