Question 1
A candidate is building a timed practice set of 50 scenario questions and wants to match the pace the real CAPM exam requires. The exam allows 3 hours for 150 questions. How long should the candidate allow for the practice set?
- 90 minutes
- 50 minutes
- 75 minutes
- 60 minutes
Show the answer
Answer: D. 60 minutes
180 minutes ÷ 150 questions = 1.2 minutes (72 seconds) per question, so 50 questions take 60 minutes. 50 minutes assumes one minute per question, which is faster than the exam pace.
Question 2
A project manager is leading an office fit-out. Three weeks ago the team added this entry to the risk register: "The flooring supplier may deliver late." This morning the supplier confirmed that the delivery will arrive ten days late. What should the project manager do first?
- Update the probability rating of the entry in the risk register and keep monitoring it
- Record the late delivery in the issue log and assign an owner to resolve it
- Record the late delivery as a new constraint on the project schedule
- Add the late delivery to the assumption log so that someone can verify it
Show the answer
Answer: B. Record the late delivery in the issue log and assign an owner to resolve it
The event is no longer uncertain, so the risk has become an issue that belongs in the issue log with an owner who carries out the planned response. Only updating the probability in the risk register is wrong because that treats a confirmed event as if it might still not happen.
Question 3
A project manager on an office relocation project is reviewing the power/interest grid. A cafe owner next door, previously rated low power and low interest, has started a petition against the move that is gaining local support. What should the project manager do first?
- Keep the cafe owner in the monitor quadrant because the original analysis has already been completed
- Send the cafe owner the 300-page relocation plan by email so they have all the details
- Remove the cafe owner from the stakeholder register because they oppose the project
- Re-plot the cafe owner on the grid and update the stakeholder register and engagement approach
Show the answer
Answer: D. Re-plot the cafe owner on the grid and update the stakeholder register and engagement approach
The grid and register are living tools, so a rise in a stakeholder's interest and influence requires re-plotting and a new engagement approach. Leaving the owner in the monitor quadrant treats the analysis as a one-time exercise, which ignores the changed circumstances.
Question 4
During a steering meeting, a senior stakeholder bluntly criticises the project manager's schedule in front of the sponsor. The project manager feels a surge of anger, pauses, thanks the stakeholder for the feedback and asks which milestones concern them most. Which component of emotional intelligence is the project manager mainly demonstrating by responding this way?
- Self-awareness
- Social skill
- Social awareness
- Self-management
Show the answer
Answer: D. Self-management
Self-management is controlling and redirecting a disruptive feeling and thinking before acting, which is what the pause and calm question show. Self-awareness is only recognising the anger; the scenario tests what the project manager does with it.
Question 5
A project coordinator is sequencing activities for a road-resurfacing project. The crew that paints lane markings follows directly behind the paving crew, so painting can begin as soon as paving begins, but not before. Both activities then run at the same time. Which logical relationship should the coordinator record between paving (predecessor) and painting (successor)?
- Finish-to-start (FS)
- Start-to-finish (SF)
- Finish-to-finish (FF)
- Start-to-start (SS)
Show the answer
Answer: D. Start-to-start (SS)
The successor cannot start until the predecessor starts, which is the start-to-start rule and allows the two activities to overlap. Finish-to-start is the nearest distractor but would force painting to wait until all paving is finished, which contradicts the scenario.
Question 6
A project manager is leading a predictive office fit-out. During a site walk-through, the client's facilities manager verbally asks for ten extra network points and says it is a quick job. No work on the request has started. What should the project manager do first?
- Ask the installation team to add the points now, since the work is small
- Revise the schedule and cost baselines to reflect the extra work
- Have the request documented as a written change request and record it in the change log
- Decline the request because the scope baseline has already been approved
Show the answer
Answer: C. Have the request documented as a written change request and record it in the change log
A verbal request is not a change request, so it must first be written down and logged before impact analysis and a decision can follow. Declining outright is wrong because the project manager should neither refuse nor agree on the spot; the request goes through the process.
Question 7
A project coordinator is supporting two agile teams on the same program. Team A averages 40 story points per iteration and Team B averages 25. The program sponsor asks the coordinator to report which team is more productive so that the weaker team can be coached. What is the best response?
- Set Team B a target of 40 points per iteration so that both teams work to the same standard
- Explain that velocity is specific to each team because story points are relative, so the two figures cannot be compared
- Convert both teams' story points into hours so that the two velocities can be ranked fairly
- Report that Team A is more productive because it completes 15 more points per iteration
Show the answer
Answer: B. Explain that velocity is specific to each team because story points are relative, so the two figures cannot be compared
Story points are a relative estimate that each team calibrates for itself, so velocity is only meaningful within one team. Setting Team B a 40-point target is the nearest distractor, but it treats velocity as a target, which only inflates estimates.
Question 8
A product owner is planning a timebox with a team whose capacity is 50 story points. The items currently classified as Must have total 36 points. The product owner wants to follow the DSDM guidance on MoSCoW. What should the product owner do?
- Accept the plan, because Must haves may fill up to 80% of the timebox effort
- Remove all Could have items so that the 36 points of Must haves fit within capacity
- Work with stakeholders to reclassify at least 6 points of Must haves, so that Musts total no more than 30 points
- Extend the timebox until the Must haves fall to 60% of the effort
Show the answer
Answer: C. Work with stakeholders to reclassify at least 6 points of Must haves, so that Musts total no more than 30 points
DSDM advises keeping Must haves to no more than 60% of timebox effort: 0.60 × 50 = 30 points, so 6 points must be reclassified. Removing Could haves does not reduce the Must total, so it leaves no real contingency against the guidance.
Question 9
A business analyst on a predictive project emailed a requirements document to six department heads a week ago. No one has replied. The delivery lead says, "No objections received, so we can start design." The analyst wants to prevent rework. What should the analyst do first?
- Walk the department heads through the key requirements with concrete examples and ask each to confirm or correct them
- Let design begin and handle any later disagreement through the change control process
- Escalate the lack of response to the sponsor and ask for a decision on whether design can start
- Record the document as approved, because the review period has passed without objections
Show the answer
Answer: A. Walk the department heads through the key requirements with concrete examples and ask each to confirm or correct them
Communication is complete only when the receiver's understanding comes back to the sender and is checked, so the analyst must create that return trip. Recording the document as approved treats silence as evidence of understanding, which it is not.
Question 10
A business analyst joins an adaptive team that is building a clinic scheduling product. The product owner asks the analyst to help with the product backlog. Two senior stakeholders then approach the analyst separately, each demanding that their own feature be moved to the top of the backlog. What should the analyst do?
- Reorder the backlog so that the feature requested by the more senior stakeholder is placed first
- Submit both requests to a change control board for formal approval before the backlog is touched
- Ask the delivery team to vote on which of the two features should be built first
- Clarify each request and its expected value, then bring the information to the product owner, who decides the order
Show the answer
Answer: D. Clarify each request and its expected value, then bring the information to the product owner, who decides the order
The analyst supports the product owner by eliciting and clarifying, but the product owner stays accountable for backlog content and order. Reordering the backlog personally is the nearest distractor and is wrong because the analyst does not take over ordering decisions.