Question 1
Elena is taking the PSM™ I assessment. With 20 minutes left, she has answered 50 of the 80 questions and is stuck on a hard one. What should she do to give herself the best chance of passing?
- Pick her best answer, mark the question if she can, and move on, because 20 minutes for 30 questions is roughly 40 seconds each
- Stop and restart the assessment later, because the time limit pauses when the window closes
- Spend as long as needed on the hard question, because every question must be answered correctly to pass
- Skip all remaining multiple-answer questions, because they do not count towards the 85% score
Show the answer
Answer: A. Pick her best answer, mark the question if she can, and move on, because 20 minutes for 30 questions is roughly 40 seconds each
The assessment has 80 questions in 60 minutes, about 45 seconds each, so Elena has to keep moving to answer them all. She does not need every question right, only 85% (68 of 80), so getting stuck on one question is the costlier mistake.
Question 2
A new Scrum Team's sponsor asks the Scrum Master why the team works in short iterations and delivers small increments instead of building to one detailed release plan. According to the Scrum Guide, what is the purpose of Scrum's iterative, incremental approach?
- To optimize predictability and to control risk
- To make sure every requirement is fixed before work starts
- To give managers more frequent status reports
- To increase the number of features delivered in each Sprint
Show the answer
Answer: A. To optimize predictability and to control risk
The Scrum Guide says Scrum uses an iterative, incremental approach to optimize predictability and to control risk. Fixing every requirement up front is a predictive approach, which is the opposite of empiricism.
Question 3
Halfway through a Sprint, the Developers find that their planned technical approach will not work. A stakeholder asks who may change the plan in the Sprint Backlog. What is the best answer?
- Nobody, because the Sprint Backlog is fixed once Sprint Planning ends.
- The Scrum Master, after the change is approved at the next Sprint Retrospective.
- The Developers, who adapt their plan each day toward the Sprint Goal.
- The Product Owner, because the Product Owner is accountable for the plan for the Sprint.
Show the answer
Answer: C. The Developers, who adapt their plan each day toward the Sprint Goal.
The Developers create the Sprint Backlog and are accountable for adapting that plan each day toward the Sprint Goal. The Product Owner is a real accountability in the Scrum Team, but the plan for the Sprint belongs to the Developers.
Question 4
A company has just started using Scrum. Stakeholders in several departments keep sending requests straight to individual Developers, and the Scrum Team is struggling to work with them. As Scrum Master, which action best fits your accountability to the wider organisation?
- Help remove the barriers between the stakeholders and the Scrum Team, and lead, train and coach the organisation in its Scrum adoption
- Ask senior management to make a formal list of which stakeholders the Developers report to
- Collect all stakeholder requests yourself and decide which ones the Developers should work on next
- Tell the stakeholders that they may not talk to the Scrum Team at all during the Sprint
Show the answer
Answer: A. Help remove the barriers between the stakeholders and the Scrum Team, and lead, train and coach the organisation in its Scrum adoption
The Scrum Guide says the Scrum Master serves the organisation by leading, training and coaching its Scrum adoption and by removing barriers between stakeholders and Scrum Teams. Deciding which requests the Developers work on would make the Scrum Master a manager and take ordering away from the Product Owner.
Question 5
On the last afternoon of Sprint Planning, the Developers have chosen their Product Backlog items, but the Scrum Team still disagrees on the wording of the Sprint Goal. One Developer suggests starting the Sprint now and agreeing on the goal at the Daily Scrum on day three. What should the Scrum Master advise?
- The Product Owner should write the Sprint Goal alone after the event so the Developers can start work at once.
- The Sprint Goal must be finalized before Sprint Planning ends, so the team should agree on it now, within the timebox.
- Starting work is acceptable as long as the Sprint Goal is agreed before the Sprint Review.
- The Sprint Goal is optional when the selected Product Backlog items are already clear.
Show the answer
Answer: B. The Sprint Goal must be finalized before Sprint Planning ends, so the team should agree on it now, within the timebox.
The Scrum Guide states that the Sprint Goal must be finalized before the end of Sprint Planning. Waiting until the Sprint Review, or until any point during the Sprint, breaks that rule and leaves the Developers with no goal to inspect progress against.
Question 6
A Scrum Team works in one-month Sprints. The new Scrum Master wants the Sprint Retrospective to stay within its timebox under the Scrum Guide. What is the longest the Sprint Retrospective can run?
- 4 hours
- 3 hours
- 1.5 hours
- 8 hours
Show the answer
Answer: B. 3 hours
The Scrum Guide caps the Sprint Retrospective at 3 hours for a one-month Sprint. 4 hours is the cap for the Sprint Review, not the Retrospective.
Question 7
During a Sprint, the Developers finish a new reporting feature and it passes its own tests. They then find that it has broken the export function delivered two Sprints ago. The Product Owner asks the Scrum Master whether the reporting feature can be counted as part of this Sprint's Increment. What is the best answer?
- Yes. The reporting feature meets its own acceptance criteria, and the export defect can go into the Product Backlog as a separate item.
- No. An Increment must be additive and thoroughly verified so that it works with all prior Increments, and the product is not usable while the export function is broken.
- Yes, if the Product Owner accepts the risk and the defect is fixed in a later hardening Sprint.
- No. Only one Increment can be produced per Sprint, so the feature has to wait until the export function is rebuilt.
Show the answer
Answer: B. No. An Increment must be additive and thoroughly verified so that it works with all prior Increments, and the product is not usable while the export function is broken.
The Scrum Guide says each Increment is additive to all prior Increments and thoroughly verified, so that all Increments work together and the result is usable. Meeting the feature's own acceptance criteria is not enough when the integrated product no longer works.
Question 8
Partway through a Sprint, a Developer asks the Scrum Master whether the Product Owner can add work to the Sprint Backlog without asking. The Scrum Master explains that the Sprint Backlog belongs to the Developers, and that the Product Owner talks to them about any change in scope. Which stance is the Scrum Master using?
- Facilitating
- Mentoring
- Teaching
- Coaching
Show the answer
Answer: C. Teaching
The Scrum Master is giving the Developer knowledge about who owns the Sprint Backlog, and that is teaching. It is not mentoring, because the Scrum Master is explaining how Scrum works, not describing what they did on another team.
Question 9
Several stakeholders find the Product Owner hard to reach. They ask the Scrum Master to collect their requests every week and pass them on to the Product Owner. What should the Scrum Master do?
- Agree to collect the requests and pass them on, because this saves the Product Owner time
- Collect the requests, rank them by business value, and give the Product Owner a recommended order
- Tell the stakeholders to send their requests straight to the Developers during the Sprint
- Facilitate direct collaboration between the stakeholders and the Product Owner, such as a session where they can discuss their needs together
Show the answer
Answer: D. Facilitate direct collaboration between the stakeholders and the Product Owner, such as a session where they can discuss their needs together
The Scrum Master serves the Product Owner by facilitating stakeholder collaboration as requested or needed, and by removing barriers between stakeholders and Scrum Teams. Acting as a go-between makes the Scrum Master a requirements proxy, which adds a barrier instead of removing one.
Question 10
During Product Backlog refinement, a Product Owner thinks the Developers' size for a high-value item is too large. She wants it halved so that it fits the release plan she has shared with stakeholders. What should happen?
- The Scrum Master settles the disagreement by averaging the two sizes.
- The Product Owner sets the final size, because she is accountable for the product's value and for the release plan.
- The Developers who will do the work keep responsibility for the size. The Product Owner may help them understand trade-offs, such as splitting the item or narrowing its scope.
- The Developers accept the smaller size and agree to work extra hours to keep the stakeholders' release date.
Show the answer
Answer: C. The Developers who will do the work keep responsibility for the size. The Product Owner may help them understand trade-offs, such as splitting the item or narrowing its scope.
The Scrum Guide makes the Developers who will do the work responsible for sizing, and lets the Product Owner influence them only by helping them understand and select trade-offs. The Product Owner's accountability for value does not give her the right to change the Developers' sizes.