Why a register matters
In Level 1 you learned that a stakeholder is anyone who can affect your project, is affected by it, or believes they are affected by it. Knowing the definition is only the start. Most surprises on a project come from people nobody listed.
This level gives you a repeatable method for finding stakeholders and a stakeholder register to record them in. The register is a structured list that you keep updating for the whole project. PMI's PMBOK Guide calls the register a living document: it changes as people join, leave or change roles.
Running example: Priya coordinates the rollout of new expense-claim software at a 400-person logistics company. Her first list has four names: the Finance Director, the IT lead, the software vendor and herself. Below, she uses four discovery techniques to build a fuller list.
Step 1: Brainstorm the obvious and the not-so-obvious
Do this: Book a 30-minute session with two or three people who know the project, such as the sponsor or a team member.
- Write down every person, group or organisation that comes to mind. Do not judge or filter yet.
- Prompt the group with categories: who pays, who decides, who builds, who uses, who supports, who approves (audit, legal, compliance) and who is outside the organisation (suppliers, customers, regulators, unions).
- Record groups as well as individuals, for example "warehouse shift supervisors".
Priya's session adds the payroll team, line managers who approve claims, internal audit and the staff representative forum.
Step 2: Review the organisation chart
Do this: Get the current org chart and go through it one department at a time.
- For each box, ask: "Does this team touch the process, the data, the budget or the people affected?"
- Look at the levels above your sponsor. A senior leader may have a view even if they never attend meetings.
- Note any vacancies, interim managers or upcoming restructures. A new appointee could become a stakeholder overnight.
Priya notices that HR owns the company travel policy, which the new software must enforce. HR goes on the list.
Step 3: Walk through the process
Do this: Follow the work from start to finish as it will run after your change.
- Choose one realistic transaction, such as "a driver claims a hotel and fuel after an overnight delivery".
- List every step and ask who does it, who receives its output, and who fixes it when it goes wrong.
- Include systems and handoffs. Every interface usually has a human owner.
On the walk-through, Priya finds that drivers submit claims from their phones, that the IT service desk will handle password resets, and that the bank file goes to a treasury analyst. None of them were on her list.
Step 4: Ask "Who else should I talk to?"
Do this: End every early conversation with the same question.
- Ask: "Who else should I talk to about this?" and "Who might be affected that we haven't thought of?"
- Write down every name you are given, along with who suggested it.
- Stop when new conversations keep giving you names you already have. That is a good sign your list is close to complete.
The treasury analyst tells Priya that the external auditors review expense controls every year. That is a stakeholder outside the company she would otherwise have missed.
Step 5: Record each stakeholder in the register
Do this: Create a spreadsheet or shared table with these columns. Use one row per person or group.
| Column | What to enter | Example |
|---|---|---|
| ID | Unique reference | S-07 |
| Name / group | Person or group name | Treasury analyst (J. Okafor) |
| Role / position | Job title or function | Treasury, Finance |
| Contact | Email, phone, location, preferred time zone | j.okafor@... / Leeds |
| Relationship to project | How they affect or are affected | Receives payment file; checks bank format |
| Internal / external | Inside or outside the organisation | Internal |
| Source of information | How you found them and who told you | Process walk-through, 14 Oct |
| Date added / last reviewed | Keeps the register current | 14 Oct / 14 Oct |
Tips:
- Write the relationship in plain words. "Affected" on its own tells a reader nothing.
- The source column shows where each entry came from and tells you who to go back to with questions.
- Store contact details only as far as your organisation's data-protection rules allow, and limit who can edit the register.
- Leave room for more columns. Later levels add analysis to this same register.
Step 6: Check for gaps before sharing
Do this: Go through this completeness checklist before you circulate the register.
- Have all four techniques been used, not just brainstorming?
- Are the people who pay, decide, build, use, support and approve all represented?
- Are external parties included (suppliers, customers, regulators, auditors, partners)?
- Are end users included, not only their managers?
- Are people who lose something (work, control, familiar tools) listed, as well as those who gain?
- Does every row have a role, a relationship and a source?
- Are vacancies and upcoming role changes noted?
- Has someone outside the core team reviewed the list?
Priya's check shows that she has listed line managers but not the staff who submit claims. She adds "all claimants" as a group, with drivers as a separate subgroup because they work mainly on mobile.
Your template to fill
Copy the table from Step 5 into your own tool. For your current project:
- Do one brainstorm, one org-chart review and one process walk-through this week.
- Add at least ten rows.
- Ask "Who else should I talk to?" in your next three conversations.
- Run the Step 6 checklist before you share the register.
Key takeaways
- Use four techniques together: brainstorming, org-chart review, process walk-through and "who else?" interviews. Each one finds people the others miss.
- Process walk-throughs reveal hidden operational stakeholders. "Who else?" questions often reveal external ones.
- Record role, contact, relationship to the project and source of information for every entry.
- Run a completeness checklist before sharing, and pay particular attention to end users, external parties and people who lose something.
- The register is a living document. Date entries and keep reviewing them.