Lesson 2: Goals, Scope and the One-Page Project Brief

Turn a vague request into clear SMART goals, an explicit in-scope and out-of-scope list, and a one-page project brief (sometimes called a project charter in the US or a project mandate in the UK).

Free to read, no account needed. Part of Project Coordination Essentials: Small Projects Done Well.

By the end of this level you'll be able to

  • Rewrite a vague request as SMART goals with measurable success criteria
  • List what is in scope, what is out of scope, the key assumptions and the constraints for a small project
  • Complete a one-page project brief template and check it with a sponsor sign-off checklist

From a Vague Request to a Clear Project

Most projects start with something like this from a manager: "Can you sort out the meeting room booking mess?" That is a request. It is not a project yet. Nobody knows what "sorted" looks like, when it is due or what is included.

In this level you will turn a request like that into three things:

  1. SMART goals: what success looks like, in measurable terms.
  2. A scope statement: what is in, what is out, and the assumptions and constraints.
  3. A one-page project brief that your sponsor signs.

The example used throughout: the Leeds office has 40 staff and 6 meeting rooms. Rooms are booked on a paper sheet, and double bookings happen about 10 times a month.

Step 1: Rewrite the Request as SMART Goals

SMART is a checklist for writing goals. George T. Doran introduced it in Management Review in 1981. His original letters were Specific, Measurable, Assignable, Realistic and Time-related. The version most often used today is:

  • Specific: says exactly what will change.
  • Measurable: has a number or test that proves it happened.
  • Achievable: realistic with the people, money and time available.
  • Relevant: matters to the organisation and to the person asking.
  • Time-bound: has a deadline.

Do this:

  1. Write down the request word for word.
  2. Ask the requester: "What would be different if this went well?" and "How would we know?"
  3. Turn each answer into a sentence that passes all five letters.
  4. Add one or two success criteria. These are the measures you will check at the end.

Example:

  • Vague: "Sort out room booking."
  • SMART: "By 31 January 2027, all 40 Leeds staff book the 6 meeting rooms through one online booking tool, and double bookings drop from about 10 a month to none during February 2027."
  • Success criteria: (a) the paper sheet has been removed; (b) no double bookings are logged in February 2027.

Check: cover the deadline and the numbers with your hand. If the goal now reads like a wish, it was not SMART.

Step 2: Draw the Scope Line

Scope is the boundary of the project. Think of it as a fence. Work inside the fence is your job. Work outside it is not, unless the sponsor formally moves the fence.

Do this:

  1. List everything the project will deliver (in scope).
  2. List the related things people might expect but the project will not deliver (out of scope).
  3. Write the out-of-scope list as carefully as the in-scope list. Most disagreements later on start with something nobody wrote down.

Example:

In scope Out of scope
Choose and set up one booking tool Catering orders for meetings
Add all 6 Leeds rooms Other offices
A 15-minute guide and drop-in session for staff New screens or video equipment in rooms

Step 3: Record Assumptions and Constraints

These two are easy to mix up:

  • An assumption is something you believe is true but have not proved. If it turns out to be wrong, the plan may change. Example: "IT will give us admin access to the calendar system by 15 November."
  • A constraint is a fixed limit you must work within. Examples: "Budget is capped at £2,000." "No changes to room layouts." "Must go live before 31 January 2027."

Do this: write three to five of each. For each assumption, add who can confirm it.

Step 4: Fill In the One-Page Project Brief

The brief collects everything above on one page. The name depends on where you work:

  • UK (PRINCE2): a project mandate is the starting request from senior management. It can be as short as an email. The project brief is the document built from it.
  • US (PMI): a project charter is the document, issued by the sponsor, that formally authorises the project and gives the project manager authority to use resources.

At this size of project they do the same job. Use whichever name your organisation uses.

Template: copy this and fill it in for the room booking example

  1. Project name:
  2. Sponsor (the person who owns the budget and signs off):
  3. Coordinator:
  4. Background (two sentences on the problem today):
  5. SMART goal(s):
  6. Success criteria:
  7. In scope:
  8. Out of scope:
  9. Assumptions:
  10. Constraints (budget, dates, rules):
  11. Target end date:
  12. Sponsor sign-off (name, date):

Keep it to one page. If it runs over, you are probably writing a plan. Planning comes in later levels.

Step 5: Check It With the Sponsor Sign-Off Checklist

Before you ask for a signature, check every box:

  • Every goal has a number or a test, plus a date.
  • Someone who did not write the brief could say what "done" means.
  • The out-of-scope list has at least three items.
  • Assumptions and constraints are listed separately.
  • The budget and end date match what the sponsor told you.
  • The whole brief fits on one page.
  • The sponsor has signed and dated it.

Then do this: walk the sponsor through it in 10 minutes. Ask: "Is anything here wrong or missing?" Make the changes, get the signature and save the signed copy where the team can find it.

Key Takeaways

  • A request is not a project. SMART goals and success criteria tell everyone what "done" means.
  • Writing down what is out of scope prevents arguments later.
  • An assumption is believed but not yet proved. A constraint is a fixed limit.
  • PRINCE2 (UK): the mandate is the starting request and the brief is built from it. PMI (US): the charter formally authorises the project.
  • Keep the brief to one page, check it against the checklist, and get the sponsor to sign it.

A 6-question knowledge check follows this lesson in the app, free and without an account.

Keep going: levels 3 and 4 are free

Create a free account to open the next two levels, save your progress and pick up where you left off. No card needed.

Next: Level 3, Stakeholders and a Simple Communication Plan.

Create a free account →See the whole course

More like this

  • Leading Your Team Through AI Adoption

    Learn to run AI adoption in a team without losing people's trust. Using a running customer service and admin case, you will find good use cases, write a team A…

    Course · Project Management · Project & Service Management · Capable · 17 levels · 4 free · Professionally curated by levelupwith.com

  • PMI Project Management Professional (PMP) Exam Prep

    Prepare for PMI's PMP exam under the outline in effect from July 2026. You will work through all 26 tasks across People, Process and Business Environment, and…

    Exam prep · PMP · Project & Service Management · Expert · 50 levels · 4 free · Professionally curated by levelupwith.com

  • Stakeholder Management: Mapping, Engaging and Reporting

    Learn to find everyone your project affects, map their power and interest, and plan how to engage them. You will practise managing expectations, handling resis…

    Course · Project Management · Project & Service Management · Capable · 18 levels · 4 free · Professionally curated by levelupwith.com

  • Kanban and Agile Delivery: Flow, Metrics and Forecasting

    Learn to design a Kanban board, set work-in-progress limits and make your team's rules explicit. You will also learn to measure flow, forecast delivery dates f…

    Course · Project Management · Project & Service Management · Capable · 18 levels · 4 free · Professionally curated by levelupwith.com

  • Lean Six Sigma Green Belt: Leading DMAIC Projects

    Take one example improvement project through every DMAIC stage, from charter to control plan, and do the statistics yourself in Excel (Minitab works too). By t…

    Course · Project Management · Project & Service Management · Expert · 42 levels · 4 free · Professionally curated by levelupwith.com

  • Product Ownership: Prepare for the Scrum.org™ PSPO™ I Assessment

    Get ready for Scrum.org's PSPO I assessment (80 questions, 60 minutes, 85% to pass, $200 an attempt, no course required). You will learn product ownership in t…

    Exam prep · Scrum.org · Project & Service Management · Capable · 16 levels · 4 free · Professionally curated by levelupwith.com